Posted on 09/21/2014, 9:02 am, by mySteinbach

CWB announced the pouring of the concrete slip for its state-of-the-art grain elevator located west of Portage La Prairie in Bloom, Manitoba is now underway.

Grain elevator

Concrete being poured at the new grain elevator located west of Portage La Prairie in Bloom.

The elevator pour began last Monday, September 15, and the 65-member crew is expected to finish within a week, with a continuous pour of one foot of concrete per hour. The 130 foot (40 meter) tall finished structure will contain more than 2,100 cubic meters of concrete and 250,000 kilograms of reinforcing steel.

“There is a flurry of 24-7 activity with trucks arriving every 40 minutes carrying the concrete required to complete the pour,” said Gord Flaten, Vice-President, Grain Procurement. “Once the slip pour is complete, the interior work will get underway throughout the fall and winter with the installation of equipment and control systems. Next summer the storage bins will be filled with grain to settle the foundation.”

Construction of CWB’s Bloom elevator was announced last March and is on track to begin receiving grain for the 2015 harvest. The elevator will feature 33,900 tonnes of storage, cleaning facilities and a 134-car loop track that will facilitate fast and efficient car loading at over 1,600 tonnes per hour.